In 2015, analysts at IDC and 451 Research said enterprise data centres were under pressure from cloud, virtualization and software-defined architecture. Executives were asking whether they wanted to own and run facilities at all. In the words of 451 Research’s Dan Harrington, companies would end up “either outsourcing to colocation or… outsourcing to cloud”.
The pressure came from several directions. Synergy Research Group found that spending on enterprise data centre equipment was flat while spending by service providers was growing quickly. Gartner forecast that by 2020, the programmatic interfaces of a software-defined data centre would be required by 75% of Global 2000 organisations adopting approaches such as DevOps.
The question facing data centre owners
Rick Villars, IDC’s vice president for data centre and cloud, said analytics and other data-heavy workloads had left owners with a dilemma. They could buy servers and storage for their own facility, or they could rent infrastructure from a provider that tunes it for the workload.
Villars put the split of data centre floor space at 77% enterprise-owned and 23% provider-owned in 2015. A decade earlier, he said, enterprises owned closer to 90%. He expected the split to approach 50-50 by 2020. Many IDC clients, he said, no longer saw data centres as a place for strategic investment. They wanted converged infrastructure, solid-state storage and virtualization to run existing applications more cheaply. Villars said some of that technology had outgrown the buildings housing it, which he called data centre obsolescence.
Harrington’s survey: consolidate first, build last
Harrington’s research asked what clients would do if they ran out of capacity tomorrow. The most common answer was to consolidate and virtualize further. Next came more cloud, including software and platform services, then colocation. About 20% said they would build a new facility.
Finance and healthcare firms were more likely to build their own, he said, because of regulatory and compliance concerns. On workload placement, 451 Research found that about 8% of workloads were then deployed in cloud. Respondents expected that to reach 21% within three years, with 14% in colocation and 65% in their own data centres, largely because of existing investment.
Harrington argued that virtualization and multicore processors had made existing hardware efficient enough that many firms had half-empty facilities and little reason to abandon them. Small and medium-sized companies, he added, were unlikely to build at all, since it was not their core business. Firms needing capacity abroad would typically rent colocation space and fit it with their own equipment. He suspected cloud was growing faster than colocation, though he said it was hard to be sure, and colocation was also rising.
Aligned’s pay-for-use colocation
Aligned Data Centers marketed a consumption-based colocation model in 2015. Its chief marketing officer, Jason Ferrara, said traditional colocation leases ran seven to 15 years, forcing customers to forecast demand far ahead. That, he argued, led to over-provisioning and idle servers.
Aligned said its model could cut the up-front commitment for power and space by up to 70%. Customers committed to 300 kilowatts, which Ferrara said was a third less than a traditional facility required. They paid for the power they actually used, on a three-year contract. The company supported up to 25 kilowatts per rack and guaranteed a power usage effectiveness of 1.15.
Mark Bauer of tenant broker Jones Lang LaSalle said customers wanted a committed supply of power with the freedom to scale it up or down. He said most hit 40% to 50% utilisation in their own facilities, against a target of about 80%.
In 2015, Aligned opened a 30-megawatt data centre in Plano, Texas, which it said used 85% less water than comparable sites. It had also started building in Phoenix. The company’s own announcement describes the first phase of Plano as 108,000 square feet and 12.5 megawatts. Full build was planned at 300,000 square feet and 30 megawatts. Aligned said the Phoenix site would be 550,000 square feet and 69 megawatts.
A customer’s view: owning versus outsourcing
Ijaaz Ullah, vice president of IT at the cloud-based health records provider Nightingale, described a split estate in 2015. Its older product ran on company-owned hardware in a Toronto facility, with a few hundred thousand dollars of equipment that the in-house team maintained and would have to replace. The redesigned second product ran on virtualized infrastructure supplied by CenturyLink.
Ullah said he planned to move the newer system to a cloud provider when the hardware refresh came due. He cited the shift from capital to operating spending as an easier sell to finance, and said each added user cost about $6 a month.
Advice on managing the move
Villars advised firms to check where they stood on capital first, because a facility built five years earlier might still be amortising. He then advised rationalising servers and applications before relocating, since combining the two causes downtime. In his words, moving would not fix inefficiencies. He said firms that had already virtualized and adopted service catalogues would find the migration to colocation, and later to cloud, much easier.
What came next for Aligned
Aligned’s Phoenix campus, listed as completed in 2017, is now put at 180 MW, and its Plano campus has since gained a second building. In September 2026, the company broke ground on Project Phoenix, a planned 2-gigawatt campus in Shippingport, Pennsylvania, which it said would run on dedicated on-site power rather than the local grid.